0%
INDUSTRIAL FILTRATION · 3D
PHOENIX PRIME
SOLUTION

Natural gas filters

Protection of regulators, meters, burners, turbines and compressors from dust, rust, sand, welding debris, water, condensate and oil aerosols.

StrainersCartridge filtersCyclonesFilter-separatorsCoalescersAdsorbers
SYSTEM DUTY

Each stage removes a different contaminant

A mesh strainer stops coarse solids. A cartridge reduces fine particulate loading. A separator drains bulk liquid, while a coalescer combines aerosol droplets for removal. H₂S, mercury and moisture require a dedicated adsorption stage.

500 µmMesh strainer
50 µmCartridge
5 µmFine filtration
0.3 µmCoalescer
FILTER TYPES

From pressure-reduction skids to turbine fuel gas

01100–500 µmMesh strainers (FG / FS / Y-type)

Washable, reusable element for PRS and GRU stations and cabinet regulators, upstream of meters and regulators.

025–50 µmCassette and cartridge filters

Replaceable mesh, synthetic-fibre or cellulose element upstream of burners, valves and precision meters.

03First stageCyclones and dust separators

Inertial removal of coarse solids and liquid without a replaceable element, for distribution and compressor stations.

04High pressureFilter-separators

Cyclonic stage and filter element in one vessel for transmission pipelines and gas distribution stations.

050.3 µmCoalescing filters

Remove oil mist, water and condensate upstream of turbines, gas engines and CNG compressors.

06H₂S · mercury · moistureAdsorption vessels

Activated carbon, zeolite or ZnO beds for sulphur removal, mercury control and gas drying.

APPLICATIONS

Gas supply stations and process consumers

0101Distribution and pressure-reduction stations

Cyclone, separator or mesh strainer at the inlet, upstream of regulation and metering.

0202Boilers, furnaces and dryers

A 10–50 µm stage upstream of burners in cement, brick, ceramics, glass, metals and food processing.

0303Cogeneration and compressors

1–5 µm fine filtration plus coalescing for turbines, gas engines and CNG stations.

ENGINEERING SELECTION

Process data that define the design

Parameter
01 / 05DN / PN
What to specify
Diameter, operating and design pressure
Design impact
Vessel, flanges and wall thickness

A typical 5–10 kPa ΔP range is not universal. The allowable drop must be checked against the regulator, burner, turbine or compressor data and the full line calculation.

CLASSIFICATION

Pressure, connection and vessel material

These ranges help define the enquiry; final execution follows design pressure, process medium and project codes.

Criterion
01 / 06Low pressure
Execution
≤ 0.005 MPa
Typical duty
GRU skids and boiler houses
SUPPLY AND COMPATIBILITY

Equipment and elements for existing lines

We supply and service equipment from leading European manufacturers and select compatible elements from drawings, dimensions and duty data. Selection may cover Pietro Fiorentini, Madas, Emerson/Tartarini, Honeywell/Elster, Parker, Pall, PECO and Jonell, without implying official partnership status.

FAQ

Natural gas filtration questions

How is the required filtration rating determined?

From the protected equipment requirement and the actual contamination. Regulators usually need a coarse stage, burners 10–50 µm, and turbines fine particulate filtration plus aerosol removal.

When is a coalescer required?

When fine oil, water or condensate droplets pass through bulk separation and threaten valves, nozzles, compressors or turbines.

Can a cartridge be washed?

Only when the manufacturer explicitly permits regeneration of that medium. Mesh elements are commonly washable; fine-fibre and coalescing elements are generally replaced.

How do I know when to replace the element?

By differential pressure reaching its limit, loss of capacity or the maintenance schedule. A differential indicator or transmitter provides the signal.

What documents are needed for selection?

Line diagram, DN/PN, flow, temperature, gas and contaminant composition, allowable ΔP, material requirements, hazardous-area data and the protected equipment specification.

Can you supply elements for an existing housing?

Yes, after model identification or element measurement. A reliable equivalent requires dimensions, seal arrangement, media, rating, flow and duty conditions.

RELATED SECTIONS

Guide and neighbouring solutions

Need a calculation for this area?

Send the line diagram, DN/PN, flow and gas composition — an engineer replies with a selection and specification within one working day.